East Quad

The renovations to University of Michigan East Quad residence hall presented quite a few challenges for the project team. East Quad required Chemical Grouting, H-Pile and Lagging, Low Head Augercast Piles, Tangential Augercast Pile Walls, Soil Nails, Drilled Low-Head Micro Piles, Push Piles, and Underpinning.

            Walbridge was the construction manager for the 90 million dollar renovations and Hardman Construction Inc (HCI) was hired for all of the above mentioned. This project was particularly difficult due to the schedule that needed to be met. On similar scope projects it would have typically taken seven months, however Walbridge required for the contract to be executed within three months.

            All together there were 21 separate areas that required some form of work from HCI. The basement provided some of the most challenging work. All of the work that was done in the basement had to be done within seven to eight feet of headroom. Most of the work in the basement was needed for all of the new underground utilities that needed to be installed. HVAC, Plumbing, Sanitary, and Electrical would all be run underground. This would allow the university extra space in the basement. All of the underground utilities were 4 to 10 feet below the bottom of the column footings. With over 200 column footings no more than 20’ apart, they needed a solution on how to excavate for the utilities without compromising the buildings structural integrity. The soils below all of the footings needed be chemical grouted. HCI facilitated the injection of over 60,000 gallons of micro fine silica cement into the basement. There were some locations that required excavation to be 10’ below the bottom of footing right next to the footing. Some of the footings were also supported with Micro or push piles. The basement area also presented HCI with the opportunity to install low-head Tangential Augercast ERS (Earth Retention System). Elevator pits were required in the basement for this to happen and HCI had to install an ERS system that would allow the concrete contractor to form the walls. The piles that were installed were 15’ long and 24” diameter with a full length cage. HCI also installed soil nails and underpinned in the basement.

            As with any construction project unknown issues and problems arise, East Quad was no different. Hardman Construction worked closely with Walbridge and Soils & Materials Engineers to solve unexpected and emergency issues all while keeping the project on time. This project was a tough job that required a company with a wide array of skills and the ability to solve tough problems. HCI completed the job successfully and satisfied the needs of the construction manager as well as the needs of the owner.

Employee Access

 login

Enter the employee access area with the login information given to you by HR. 

Contact Us

HARDMAN CONSTRUCTION

 

242 S. Brye Road

Ludington, MI 49431

 

231-845-1236 phone

 

231-845-0422 fax

 

Copyright 2015 Hardman Construction. All Rights Reserved.

Email Us

Email:
Subject:
Message:
What is 2+7?